Swimming Center Hosingen

Project Details

Year : 2013
Owner :sispolo – parc hosingen
Total gross floor area:7,800 m²
Total surface area:+- 1 ha
Built volume:+- 40,000 m³
Total investment cost:+- 13 million euros
Design phase:2010 – 2011
Time to completion:2011 – 2013

Description

The project comprises :

  • construction of the swimming pool, including gymnasiums, changing rooms and a catering area with kitchen,
  • structural steelwork, woodwork and reinforced concrete,
  • exterior fittings and infrastructure.

The engineer’s mission includes :

  • preliminary design studies,
  • execution project,
  • preparation of tender documents,
  • supervision of execution.