Year: 2017
Architects : bob strotz architecture bsa
Owner: Ministry of Public Works
Total surface area: +- 4,500 m²
Built volume: +- 18,000 m³
Total investment cost: +- 14.5 million euros
Design time: 2001 – 2008
Time to completion: 2008 – (in progress)
In 2001, the A.B.P. decided to replace the existing infrastructure of the Police Intervention Center with a new building.
The project was to be built on the land occupied at the time by the FRISCH hotel, which had to be demolished.
However, due to a number of unforeseeable problems that arose during the demolition of the hotel, planning took several years and the start of the new construction was postponed until 2008.
The new building includes public reception areas, administrative areas, interrogation and detention rooms, as well as infrastructure for the vehicle fleet and staff accommodation.
Our mission included pre-project studies, the execution project, tender documents, technical assistance and follow-up of the execution, as well as the elaboration of the external landscaping.