Cookies are used to ensure that the website works properly, for security, to measure and analyse website traffic, and to improve the user experience. Your consent for the installation of cookies that are not strictly necessary is optional and may be withdrawn at any time.
These cookies are necessary for the website to function, contribute to the safe use of the website and cannot be switched off in our system.
These cookies enable the website to provide enhanced functionality and personalisation. They may be set by us or by third party providers whose services we have added to our pages. If you do not allow these cookies then some or all of these services may not function properly.
We use these cookies in order to improve our services, offer you more appropriate products and services, collect statistical data about website usage and get more detailed information about the traffic on our website.
Year: 2017
Architects : bob strotz architecture bsa
Owner: Ministry of Public Works
Total surface area: +- 4,500 m²
Built volume: +- 18,000 m³
Total investment cost: +- 14.5 million euros
Design time: 2001 – 2008
Time to completion: 2008 – (in progress)
In 2001, the A.B.P. decided to replace the existing infrastructure of the Police Intervention Center with a new building.
The project was to be built on the land occupied at the time by the FRISCH hotel, which had to be demolished.
However, due to a number of unforeseeable problems that arose during the demolition of the hotel, planning took several years and the start of the new construction was postponed until 2008.
The new building includes public reception areas, administrative areas, interrogation and detention rooms, as well as infrastructure for the vehicle fleet and staff accommodation.
Our mission included pre-project studies, the execution project, tender documents, technical assistance and follow-up of the execution, as well as the elaboration of the external landscaping.